Mesa Hills Phase 1

S Mesa Hills and Bluff Canyon Rd, El Paso, TX 79912, El Paso, TX, 79912
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024022284
$8.0M
Project Value
65,000
Square Feet
$123/sqft
Cost/SqFt
1y 3mo
Duration
Registered:Jul 2, 2024
Start:Oct 1, 2024
Target:Dec 31, 2025
Remaining:5 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

New construction of 64 apartment units in 4 buildings with a community center.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 2, 2024
Construction Start
October 1, 2024
Expected Completion
December 31, 2025