๐Project Registered๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Floresville Police Department Law Enforcement Center
914 C Street, Floresville, TX 78114, Floresville, TX, 78114
Pre-Construction15%
๐Project Metrics
TDLR #TABS2024025767$4.5M
Project Value
6,400
Square Feet
$703/sqft
Cost/SqFt
8 months
Duration
Registered:Aug 19, 2024
Start:Sep 2, 2024
Target:May 1, 2025
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
Removing and replacing utilities and fencing, constructing a new Law Enforcement Center, installing a new pre-engineered metal building, constructing a new parking lot, and security infrastructure in accordance with the contract documents.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 19, 2024
Construction Start
September 2, 2024
Expected Completion
May 1, 2025