๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

EPW Advanced Water Purification Facility (AWPF)

10000 Southside, El Paso, TX 79927, El Paso, TX, 79927
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024026110
$48.0M
Project Value
40,500
Square Feet
$1.19K/sqft
Cost/SqFt
3y 1mo
Duration
Registered:Aug 22, 2024
Start:Nov 1, 2024
Target:Nov 1, 2027
Remaining:674 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

water purification facility to include process room, administrative areas, educational and research spaces.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 22, 2024
Construction Start
November 1, 2024
Expected Completion
November 1, 2027