๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Prosper ISD | New Middle School No. 8

E FM 1461, Celina, TX 75071, Celina, TX, 75071
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025000485
$120.0M
Project Value
1
Square Feet
$120000.00K/sqft
Cost/SqFt
1y 9mo
Duration
Registered:Sep 9, 2024
Start:Oct 23, 2024
Target:Jul 8, 2026
Remaining:135 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Prosper ISD | New Middle School No. 8

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 9, 2024
Review Complete
September 9, 2024
Construction Start
October 23, 2024
Expected Completion
July 8, 2026

๐Ÿ“Location & Views

Open in MapsGet Directions|33.16096, -96.60610

Get alerts for Collin

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists