๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Episcopal High School - Chapel
4650 Bissonnet, Bellaire, TX 77401, Bellaire, TX, 77401
Construction50%
๐Project Metrics
TDLR #TABS2025005431$24.0M
Project Value
24,000
Square Feet
$1.00K/sqft
Cost/SqFt
1y 8mo
Duration
Registered:Nov 12, 2024
Start:Jan 5, 2026
Target:Aug 27, 2027
Remaining:607 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Demolition of the existing chapel and construction of a new 21,000 SF chapel with seating capacity for 960 people and a choir loft balcony. Renovation of 3000 sf in the existing convent admin building for treatment and counseling offices.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 12, 2024
Construction Start
January 5, 2026
Expected Completion
August 27, 2027
๐Related Projects
๐คSame Owner
$54.0M totalProperty Owner
๐ค
Episcopal High School
Contact: Robert Buckelew
3 projects ยท $54.0M
View all projects
4621 Fournace Street, Bellaire, Texas 77401