๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

North Beach Drainage Improvements(Phase 1),Beach Ave(Bond 2018),Gulfspray Ave(Bond 2018),Eco Park

3826 Surfside Blvd, Corpus Christi, TX 78402, Corpus Christi, TX, 78402
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025006369
$3.7M
Project Value
1,021,451
Square Feet
$4/sqft
Cost/SqFt
1y 8mo
Duration
Registered:Nov 25, 2024
Start:Mar 3, 2025
Target:Nov 3, 2026
Remaining:253 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

This project includes the construction of a new central drainage canal (4600 LF), Park improvements including two (2) concrete pedestrian trails, Wastewater and water improvements, & two (2) road reconstruction and pedestrian improvements.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 25, 2024
Review Complete
November 25, 2024
Construction Start
March 3, 2025
Expected Completion
November 3, 2026

๐Ÿ“Location & Views

Open in MapsGet Directions|27.82578, -97.38637

Get alerts for Nueces

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists