๐Review Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
METRO TMC TC Elevator Replacement
6910 Fannin, Houston, TX 77030, Houston, TX, 77030
Construction50%
๐Project Metrics
TDLR #TABS2025006377$3.8M
Project Value
800
Square Feet
$4.75K/sqft
Cost/SqFt
2 years
Duration
Registered:Nov 25, 2024
Start:Jan 1, 2025
Target:Dec 31, 2026
Remaining:369 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Four existing traction elevators will be replaced with four hydraulic elevators. As well as an addition of an electrical room and machine rooms.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 25, 2024
Construction Start
January 1, 2025
Expected Completion
December 31, 2026
๐Related Projects
Property Owner
๐ค
METROPOLITAN TRANSIT AUTHORITY HARRIS COUNTY
Contact: Mustaque Rumi
4 projects ยท $74.7M
View company profile
1900 Main St., Houston, Texas 77002