๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
SH 71 Intersection Improvements
SH 71 at Tucker Hill Ln, TX, 78602
Construction50%
๐Project Metrics
TDLR #TABS2025007159$67.6M
Project Value
152,000
Square Feet
$445/sqft
Cost/SqFt
2y 5mo
Duration
Registered:Dec 9, 2024
Start:Jul 1, 2025
Target:Nov 27, 2027
Remaining:700 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construct Grade-Separated Interchange at Tucker Hill Ln with EB and WB Frontage Roads, Sidewalk and Curb Ramps
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 9, 2024
Review Complete
December 9, 2024
Construction Start
July 1, 2025
Expected Completion
November 27, 2027