Opening ~Mar 2027๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

2024 Bond EFISD - Transportation

565 FM 451, Marshall, TX, 75672

2024 Bond EFISD - Transportation is a new construction project at 565 FM 451, Marshall, in Harrison County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Mar 2027. The project has an estimated value of $2.3M across about 5,106 sq ft.

Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025007273
$2.3M
Project Value
5,106
Square Feet
$441/sqft
Cost/SqFt
2y 1mo
Duration
Registered:Dec 10, 2024
Start:Feb 1, 2025
Target:Mar 1, 2027
Remaining:219 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

2024 Bond EFISD - Transportation is a New Construction project located at 565 FM 451 in Marshall, Texas. The project has an estimated value of $2.3M covering 5,106 sq ft. Elysian Fields Independent School District is the property owner and Harris Craig Architects, Inc. is the design firm of record. The project was registered with TDLR on December 10, 2024.

โ“Frequently Asked Questions

What is 2024 Bond EFISD - Transportation?

2024 Bond EFISD - Transportation is a new construction project at 565 FM 451 in Marshall, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New 5,106 sf transportation facility.

Is 2024 Bond EFISD - Transportation open in Marshall?

2024 Bond EFISD - Transportation is still under construction in Marshall, TX, with an estimated completion of Mar 2027 according to its TDLR registration.

Where is 2024 Bond EFISD - Transportation located?

2024 Bond EFISD - Transportation is located at 565 FM 451, Marshall, TX, 75672, in Harrison County.

Who is the owner or developer of 2024 Bond EFISD - Transportation?

Elysian Fields Independent School District is the property owner/developer of record for 2024 Bond EFISD - Transportation, per its TDLR project registration.

Who is the architect or design firm for 2024 Bond EFISD - Transportation?

Harris Craig Architects, Inc. is the design firm of record for 2024 Bond EFISD - Transportation, according to its TDLR filing.

How much does 2024 Bond EFISD - Transportation cost and how big is it?

2024 Bond EFISD - Transportation has an estimated construction value of $2.3M and approximately 5,106 square feet (about $441/sqft), based on its TDLR filing.

๐Ÿ“‹Scope of Work

New 5,106 sf transportation facility.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 10, 2024
Review Complete
December 10, 2024
Construction Start
February 1, 2025
Expected Completion
March 1, 2027

๐Ÿ“…Project Timeline

Filed

Dec 10, 2024

Review Complete

Dec 10, 2024

Inspection Complete

Closed

๐Ÿ“Location & Views

Open in MapsGet Directions|32.37399, -94.17402

Get alerts for Harrison

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists