๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
McClendon Park East Playground Improvements
740 W Kimball St, Mansfield, TX 76063, Mansfield, TX, 76133
Construction50%
๐Project Metrics
TDLR #TABS2025011653$450K
Project Value
15,000
Square Feet
$30/sqft
Cost/SqFt
5 months
Duration
Registered:Feb 11, 2025
Start:Mar 3, 2025
Target:Aug 12, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
new playground with sidewalk improvements.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 11, 2025
Review Complete
February 11, 2025
Construction Start
March 3, 2025
Expected Completion
August 12, 2025
๐Related Projects
๐Nearby Projects
Within 1 kmSidewalk Improvement for W Kimball Street, 2nd Ave, 1st Ave
200 & 400 blk of W Kimball St, 100 blk, 1st Ave, 100 blk 2nd Ave, Mansfield, TX 76063ยท$302K
Cook Cabin Relocation & Restoration
604 W. Broad Streetยท$400K
Paving Improvements for Elizabeth Lane
Elizabeth Laneยท$107K
Mans Best Field Dog Park Phase II
610 W. Broad Street, Mansfield, TX 76063ยท$920K
Property Owner
๐ค
Mansfield Parks Department
Contact: Garett Smith
View company profile
405 Industrial Blvd, Mansfield, Tx 76063, Mansfield, Texas 76063