๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
True Dental
5009 Schertz Parkway, Schertz, TX, 78154
Construction50%
๐Project Metrics
TDLR #TABS2025018189$596K
Project Value
3,860
Square Feet
$155/sqft
Cost/SqFt
4 months
Duration
Registered:May 5, 2025
Start:Jul 7, 2025
Target:Oct 31, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
tenant finish-out
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 5, 2025
Review Complete
May 5, 2025
Construction Start
July 7, 2025
Expected Completion
October 31, 2025
Property Owner
๐ค
TRUE DENTAL TX
Contact: Stacy Trieu
View company profile
5009 Schertz Parkway, Schertz, Texas 78154