๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Dollar General
Centerpoint Road, San Marcos, TX, 78666
Construction50%
๐Project Metrics
TDLR #TABS2025024340$1.5M
Project Value
10,205
Square Feet
$147/sqft
Cost/SqFt
5 months
Duration
Registered:Jul 25, 2025
Start:Dec 1, 2025
Target:May 5, 2026
Remaining:130 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New Construction
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 25, 2025
Review Complete
July 25, 2025
Construction Start
December 1, 2025
Expected Completion
May 5, 2026
๐Related Projects
๐คSame Owner
$4.0M totalProperty Owner
๐ค
BLACKBURN HOLDINGS
Contact: Patrick Reeves
3 projects ยท $4.0M
View company profile
825 Sisk Avenue Suite 200, Oxford, Mississippi 38655