๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Arrow Point
FM 1431, Cedar Park, TX, 78613
Construction50%
๐Project Metrics
TDLR #TABS2025024840$6.0M
Project Value
54,000
Square Feet
$111/sqft
Cost/SqFt
3 months
Duration
Registered:Jul 31, 2025
Start:Nov 1, 2025
Target:Feb 1, 2026
Remaining:36 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
3 office/warehouse sytle buildings approx. 54,000 sf, retaining wall, pavement, utilities, sidewalks, grading, etc...
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 31, 2025
Review Complete
July 31, 2025
Construction Start
November 1, 2025
Expected Completion
February 1, 2026
๐Related Projects
Property Owner
๐ค
Central Southwest Texas Development, LLC
Contact: Austin McWilliams
4 projects ยท $8.2M
View all projects
1703 W. 5TH ST SUITE 850, Austin, Texas 78703