๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

DAL-595 New Fuel Center

1312 Rancho Canyon Way, Fort Worth, TX, 76052
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025025641
$1.1M
Project Value
179
Square Feet
$6.15K/sqft
Cost/SqFt
8 months
Duration
Registered:Aug 12, 2025
Start:Jan 26, 2026
Target:Sep 18, 2026
Remaining:208 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Construct New Fuel Center on Kroger-owned lot. Total SF is 179.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 12, 2025
Review Complete
August 12, 2025
Construction Start
January 26, 2026
Expected Completion
September 18, 2026

๐Ÿ“Location & Views

Open in MapsGet Directions|32.99992, -97.38959

Get alerts for Denton

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists