๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
183A SBFR Shared Use Path South of San Gabriel Pkwy Project
183A Southbound Frontage Road South of San Gabriel, Leander, TX, 78641
Construction50%
๐Project Metrics
TDLR #TABS2025027063$570K
Project Value
21,650
Square Feet
$26/sqft
Cost/SqFt
3 months
Duration
Registered:Aug 29, 2025
Start:Aug 1, 2025
Target:Oct 30, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
This project will construct a 2,165 LF section of SUP along SBFR south of San Gabriel intersection within CTRMA right of way. The project involves about 21,650 SF of concrete SUP pavement to ensure north-south continuity for pedestrian/bike traffic.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 29, 2025
Review Complete
August 29, 2025
Construction Start
August 1, 2025
Expected Completion
October 30, 2025
Property Owner
๐ค
CENTRAL REGIONAL MOBILITY AUTHORITY CTRMA
Contact: Mike Sexton
View company profile
3300 N IH-35, Suite 300, Austin, Texas 78705
Design Firm
๐๏ธ
ATKINS NORTH AMERICA
View company profile