7-Eleven_Store#41933 is a renovation/alteration project at 2646 S Jupiter Road, Garland, in Dallas County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed May 2026). The project has an estimated value of $125K across about 4,614 sq ft.
Final inspection completed, awaiting project closure
7-Eleven_Store#41933 is a Renovation/Alteration project located at 2646 S Jupiter Road, Garland, TX 75041 in Garland, Texas. The project has an estimated value of $125K covering 4,614 sq ft. 7-Eleven Inc. is the property owner. The project was registered with TDLR on September 12, 2025.
7-Eleven_Store#41933 is a renovation/alteration project at 2646 S Jupiter Road in Garland, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: The scope of work includes replacing existing food service equipment,casework,making minor wall modifications, installing new wall finish, and carrying out minor electrical, and plumbing work.
Construction on 7-Eleven_Store#41933 is complete โ TDLR records show the project passed its required accessibility inspection in May 2026. The building is finished and very likely open.
7-Eleven_Store#41933 is located at 2646 S Jupiter Road, Garland, TX, 75041, in Dallas County.
7-Eleven Inc. is the property owner/developer of record for 7-Eleven_Store#41933, per its TDLR project registration.
7-Eleven_Store#41933 has an estimated construction value of $125K and approximately 4,614 square feet (about $27/sqft), based on its TDLR filing.
The scope of work includes replacing existing food service equipment,casework,making minor wall modifications, installing new wall finish, and carrying out minor electrical, and plumbing work.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Filed
Sep 12, 2025
Review Complete
Feb 18, 2026
Inspection Complete
May 1, 2026
Closed
159d
Review duration
72d
Construction phase