๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Talia Masterplan Community Phase 1B Public

9850 FM 2757, Forney, TX, 75126
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2026001110
$1.2M
Project Value
28,000
Square Feet
$42/sqft
Cost/SqFt
6 months
Duration
Registered:Sep 17, 2025
Start:Sep 12, 2025
Target:Mar 12, 2026
Remaining:76 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

28,000 sf of pedestrian hardscape area include sidewalk and seating; a gas fire place, 13,300 sf of shrub and ground cover planting, 411,300 sf of sod and seed and 226 shade and ornamental trees

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 17, 2025
Review Complete
September 17, 2025
Construction Start
September 12, 2025
Expected Completion
March 12, 2026

๐Ÿ“Location & Views

Open in MapsGet Directions|32.69182, -96.49457

Quick Actions

TDLR ID: TABS2026001110

Registered Accessibility Specialist

๐Ÿ“‹
MARC S,FRAME
RAS #1164
6 SHADY OAKS CT, TROPHY, TX 76262