Sanford Farms Phase 1 Landscape Improvements

NW corner junc. Kickapoo Rd & Betka Road, Waller, TX, 77484
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2026004140
$1.3M
Project Value
778,798
Square Feet
$2/sqft
Cost/SqFt
4 months
Duration
Registered:Oct 23, 2025
Start:Jan 14, 2026
Target:Apr 30, 2026
Remaining:67 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Sidewalks, Tub. Steel Fencing, Site Furniture, Fountains in Det. ponds, Irrigation, Landscape, Hydromulch & Solid Sod

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 23, 2025
Review Complete
October 23, 2025
Construction Start
January 14, 2026
Expected Completion
April 30, 2026

๐Ÿ“Location & Views

Open in MapsGet Directions|29.81198, -95.37412