๐Ÿ“‹Project Registered๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Store#40685

5302 E Highway 107, Edinburg, TX, 78542
Pre-Construction15%

๐Ÿ“ŠProject Metrics

TDLR #TABS2026005412
$116K
Project Value
4,313
Square Feet
$27/sqft
Cost/SqFt
1 year
Duration
Registered:Nov 7, 2025
Start:Dec 1, 2025
Target:Nov 23, 2026
Remaining:332 days
๐Ÿ“‹

Project Registered

Project has been registered with TDLR and is in pre-construction phase

๐Ÿ“‹Scope of Work

Scope of work is limited to install new and/or relocate existing beverage equipment, gondolas, and food warming equipment. Modify existing plumbing and electrical systems as needed for the new and relocated equipment scope.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 7, 2025
Construction Start
December 1, 2025
Expected Completion
November 23, 2026