MCD CICU_Phase 3 CICU is a renovation/alteration project at 7777 Forrest Lane, Dallas, TX 75230, in Dallas County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Apr 2026). The project has an estimated value of $18.5M across about 26,547 sq ft.
Final inspection completed, awaiting project closure
MCD CICU_Phase 3 CICU is a Renovation/Alteration project located at 7777 Forrest Lane, Dallas, TX 75230 in Dallas, Texas. The project has an estimated value of $18.5M covering 26,547 sq ft. HCP DR MCD LLC is the property owner and Perkins+Will is the design firm of record. The project was registered with TDLR on November 19, 2025.
MCD CICU_Phase 3 CICU is a renovation/alteration project at 7777 Forrest Lane, Dallas, TX 75230 in Dallas, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Interior major renovation to add pediatric CICU patient rooms and associated support spaces.
Construction on MCD CICU_Phase 3 CICU is complete โ TDLR records show the project passed its required accessibility inspection in Apr 2026. The building is finished and very likely open.
MCD CICU_Phase 3 CICU is located at 7777 Forrest Lane, Dallas, TX 75230, Dallas, TX, 75230, in Dallas County.
HCP DR MCD LLC is the property owner/developer of record for MCD CICU_Phase 3 CICU, per its TDLR project registration.
Perkins+Will is the design firm of record for MCD CICU_Phase 3 CICU, according to its TDLR filing.
MCD CICU_Phase 3 CICU has an estimated construction value of $18.5M and approximately 26,547 square feet (about $697/sqft), based on its TDLR filing.
Interior major renovation to add pediatric CICU patient rooms and associated support spaces.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Filed
Nov 19, 2025
Review Complete
Feb 11, 2026
Inspection Complete
Apr 17, 2026
Closed
84d
Review duration
65d
Construction phase