๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Valvoline

1288 N Central Expressway, Anna, TX, 75409
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2026007610
$1.4M
Project Value
3,447
Square Feet
$420/sqft
Cost/SqFt
6 months
Duration
Registered:Dec 10, 2025
Start:Jun 8, 2026
Target:Dec 8, 2026
Remaining:289 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

New Construction Valvoline with Lube Pit

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
+6d
December 10, 2025
Review Complete
December 16, 2025
Construction Start
June 8, 2026
Expected Completion
December 8, 2026

๐Ÿ“Location & Views

Open in MapsGet Directions|33.36341, -96.58320

Get alerts for Collin

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists