πReview Completeπ§ Alteration/Renovation
MISD Gray Elementary School Renovation
Construction50%
πProject Metrics
TDLR #TABS2026008601$3.7M
Project Value
β
Square Feet
β
Cost/SqFt
2 months
Duration
Registered:Dec 19, 2025
Start:May 30, 2026
Target:Aug 1, 2026
Remaining:155 days
π
Review Complete
Design review complete, construction may proceed
π Compliance Timeline
Project Registered
+13dDecember 19, 2025
Review Complete
January 1, 2026
Construction Start
May 30, 2026
Expected Completion
August 1, 2026