๐Project Registered๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
RM 1061 (CSJ: 1245-02-052, etc.)
From: N Coulter Street To: BUS 40D, Amarillo, TX 79124, Amarillo, TX, 79124
Pre-Construction15%
๐Project Metrics
TDLR #TABS2026010070$9.8M
Project Value
185,241
Square Feet
$53/sqft
Cost/SqFt
7 months
Duration
Registered:Jan 14, 2026
Start:Jun 29, 2026
Target:Jan 29, 2027
Remaining:379 days
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
For the construction of shared use path, grading, ACP, concrete, sidewalk, ADA curb ramps, pavement markings, signing and signals.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 14, 2026
Construction Start
June 29, 2026
Expected Completion
January 29, 2027
๐Related Projects
๐คSame Owner
$32.6M total๐๏ธSame Design Firm
$716.7M totalProperty Owner
๐ค
TxDOT District: Amarillo
4 projects ยท $32.6M
View all projects
5715 Canyon Drive, Amarillo, Texas 79110
Design Firm
๐๏ธ
WSP USA, Inc.
4 projects ยท $716.7M
View all projects
31020Oak Lawn Avenue , Suite 450, Dallas, Texas 75219