Fume Hood Replacement Earl Warren HS
9411 Military Drive West, San Antonio, TX 78251, San Antonio, TX, 78251
Construction50%
๐Project Metrics
TDLR #TABS2026011309$1.3M
Project Value
50,000
Square Feet
$26/sqft
Cost/SqFt
8 months
Duration
Registered:Jan 30, 2026
Start:Mar 1, 2026
Target:Oct 31, 2026
Remaining:251 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Renovation of Fume Hoods and added Control Panels
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
+21dJanuary 30, 2026
Review Complete
February 20, 2026
Construction Start
March 1, 2026
Expected Completion
October 31, 2026