Home/Site Plans/Interport Phase 2, floodplain Modifications
βœ… Approved and Released

Interport Phase 2, floodplain Modifications

The applicant is proposing floodplain modifications with associated improvements.

πŸ“ 3700-4044 E EB SH 71, Austin, TXπŸ“„ Site Plan
Entitled100%
Site area
28.90 acres
Timeline
Applied: Jul 12, 2007
Updated: Jan 4, 2008

πŸ“ŠSite Plan Metrics

#10051539
28.90 acres
Site Area
βœ…

Approved and Released

Step 5 of 5: Released βœ“

Site plan fully approved and released. All conditions cleared. Ready for construction permitting.

Next:Pull building permits to begin construction.

πŸ“‹Scope of Work

The applicant is proposing floodplain modifications with associated improvements.

πŸ“…Entitlement Timeline

Application Filed
+30d
July 12, 2007
In Review
+146d
August 11, 2007
Approved
January 4, 2008

πŸ“Location & Views

Open in MapsGet Directions|30.22768, -97.77220

🀝 Project Team

🏠 Owner Contact
B
Bob Stevens
Lone Star Infrastructure
πŸ“ Applicant Contact
T
TRACY WADE
Urban Design Group

Zoning & Land Use

Current Zoning
N/A
Existing Use
Agricultural
Proposed Use
Open Space

Case Manager

πŸ‘€
Kevin Shunk
City of Austin Development Services

Explore Area

πŸ“Œ Case Details

Case Number10051539
Case TypeSite Plan
Sub TypeSite Plan Administrative
Permit NumberSP-2007-0408D
Jurisdictionβ€”
Property RSN3293017