✅ Approved and ReleasedDistrict 6
Premier Storage 620
The applicant is proposing a 4 story self storage building with associated improvements.
📍 14926 N SB FM 620 RD, AUSTIN, TX, 78717📄 Site Plan🏛️ AUSTIN LTD
Entitled100%
Timeline
Applied: Aug 30, 2022
Updated: Aug 8, 2025
📊Site Plan Metrics
#13008484ABC Portal →
FAR:—
Impervious:60.0%
Applied:Aug 30, 2022
Approved:Mar 27, 2024
✅
Approved and Released
Step 5 of 5: Released ✓Site plan fully approved and released. All conditions cleared. Ready for construction permitting.
Next:Pull building permits to begin construction.
📋Scope of Work
The applicant is proposing a 4 story self storage building with associated improvements.
📅Entitlement Timeline
Application Filed
+30dAugust 30, 2022
In Review
+545dSeptember 29, 2022
Approved
March 27, 2024
🤝 Project Team
🏠 Owner Contact
J
John Barizza
620 JMJ Ltd.
📝 Applicant Contact
T
Thomas Lombardi
Kimley-Horn
💰 Fees
Landscape Inspection
$375.00
OutstandingTechnology Surcharge-DSD
$15.00
OutstandingTree Mitigation Fee
$46,550.00
OutstandingUDS Engineering Plan Review Update
$602.00
OutstandingEnvironmental Inspection (deposit)
$4,347.00
OutstandingTechnology Surcharge-DSD
$173.88
OutstandingBasic Notification
$261.90
OutstandingCity Arborist Site Plan/Subdivision Review
$2,183.40
OutstandingConsolidated Site Plan-Dev
$14,735.70
OutstandingUDS Engineering Plan Review
$241.00
OutstandingPARD-Site Plan/Subdivision Review Fee
$717.00
OutstandingAE - Site Plan Review
$162.00
OutstandingFIRE-Fire Site Plan Review
$340.00
OutstandingWPD- Site Plan Hydrogeologist Review
$2,211.00
OutstandingTechnology Surcharge-DSD
$775.68
OutstandingTPW-SP-Site Plan Consolidated
$6,320.00
OutstandingCompleteness Check Fee
$406.00
OutstandingWPD-Site Plan Completeness Check
$34.00
OutstandingTechnology Surcharge-DSD
$17.60
Outstanding📐 Nearby Site Plans
AUSTIN ENERGY NORTHWEST SUBSTATION
Approved and Released • AUSTIN • Mar 2, 2007
SPRINT COMMUNICATIONS TOWER & COMPOUND
Approved and Released • AUSTIN • Mar 2, 2007
Parmer Village Duplexes
Approved and Released • AUSTIN • Oct 30, 2014
THE VILLAGE (WITHDRAWAL & RESUBMITTAL OF SP-04-0214D)
Expired • AUSTIN • Mar 2, 2007
THE VILLAGE (Site Plan Extension)
Approved and Released • AUSTIN • Apr 16, 2010
THE VILLAGE
Withdrawn • AUSTIN • Mar 2, 2007
THE VILLAGE (Site Plan Extension)
Expired • AUSTIN • Nov 24, 2009
THE VILLAGE (RESUBMITTAL OF SP-03-0454D)
Withdrawn • AUSTIN • Mar 2, 2007
THE VILLAGE
Approved and Released • AUSTIN • Apr 16, 2010
JEFFERSON CENTER
Closed • AUSTIN • Mar 2, 2007
JEFFERSON CENTER
Approved and Released • AUSTIN • Mar 2, 2007
JEFFERSON CENTER - PHASE II (SITE PLAN EXTENSION)
Approved • AUSTIN • Mar 2, 2007
Key Stakeholders
Zoning & Land Use
Current Zoning
CS-CO / EJT
Existing Use
Commercial
Proposed Use
Commercial
Environmental & Geographic
Watershed ClassSuburban Watershed
🎓 School DistrictROUND ROCK ISD
Impervious Cover60.0%
Case Manager
👤
Gabriel Guerrero Jr
City of Austin Development Services
Explore Area
📌 Case Details
Case Number13008484
Case TypeSite Plan
Sub TypeSite Plan Administrative
Permit NumberSP-2022-1392C
JurisdictionAUSTIN LTD
TCAD IDR055271
Property RSN249615
🔗 Related Cases
Legal Description
AW0169 - Davy, T.p. Sur.