β
Approved and Released
SOUTHWESTERN BELL - TAMARRON BLVD.
Site plan fully approved and released. All conditions cleared. Ready for construction permitting.
π TAMARRON BLVD, Austin, TXπ Site Plan
Entitled100%
Timeline
Applied: Sep 23, 1993
Updated: Mar 2, 2007
β
Approved and Released
Step 5 of 5: Released βSite plan fully approved and released. All conditions cleared. Ready for construction permitting.
Next:Pull building permits to begin construction.
π Entitlement Timeline
Application Filed
+30dSeptember 23, 1993
In Review
+4878dOctober 23, 1993
Approved
March 2, 2007
π€ Project Team
π Owner Contact
R
Randy Johnson
π Nearby Site Plans
STATE FARM INSURANCE
Approved and Released β’ AUSTIN β’ Mar 2, 2007
SOUTH LAMAR SERVICE CENTER APPROACH MAIN
Approved and Released β’ AUSTIN β’ Mar 2, 2007
Red's Porch
Expired β’ AUSTIN β’ Nov 29, 2009
Red's Porch
Expired β’ AUSTIN β’ Feb 15, 2013
Loop 360 Landfill Remediation
Approved and Released β’ AUSTIN β’ Oct 24, 2011
Loop 360 Landfill Remediation
Expired β’ AUSTIN β’ Jan 3, 2011
GAINES RANCH EXECUTIVE PARK II
Approved and Released β’ AUSTIN β’ Mar 2, 2007
South Lamar Driveway
Approved and Released β’ AUSTIN β’ Dec 13, 2013
LA QUINTA - GAINES RANCH
Approved and Released β’ AUSTIN β’ Mar 2, 2007
South Lamar Boulevard Mixed Use
Approved and Released β’ AUSTIN β’ Aug 16, 2012
W.O.B Expansion
Approved and Released β’ AUSTIN β’ Mar 21, 2014
W.O.B.
Approved and Released β’ AUSTIN β’ Jul 29, 2013
Case Manager
π€
Javad Oskouipour
City of Austin Development Services
Explore Area
π Case Details
Case Number153144
Case TypeSite Plan
Sub Typeβ
Permit NumberSP-93-0429DS
Jurisdictionβ
Property RSN7721