β
Approved and Released
MCBEE ELEMENTARY
Site plan fully approved and released. All conditions cleared. Ready for construction permitting.
π W BRAKER LN, AUSTIN, TXπ Site Plan
Entitled100%
Timeline
Applied: Jun 21, 1999
Updated: Mar 2, 2007
β
Approved and Released
Step 5 of 5: Released βSite plan fully approved and released. All conditions cleared. Ready for construction permitting.
Next:Pull building permits to begin construction.
π Entitlement Timeline
Application Filed
+30dJune 21, 1999
In Review
+2781dJuly 21, 1999
Approved
March 2, 2007
Active
September 29, 1999
π€ Project Team
π Owner Contact
M
Mark Brewster
π Nearby Site Plans
Presidium at Waterford
Expired β’ AUSTIN β’ Oct 21, 2019
Metric Industrial
Approved and Released β’ AUSTIN β’ Jan 21, 2022
WATERFORD CENTRE II
Approved and Released β’ AUSTIN β’ Mar 2, 2007
VICTORY CENTER
Approved and Released β’ AUSTIN β’ Mar 2, 2007
Presidium at Waterford
Approved and Released β’ AUSTIN β’ Jul 30, 2024
Presidium at Waterford
Approved and Released β’ AUSTIN β’ Aug 1, 2024
TECHLINE, INC.
Approved and Released β’ AUSTIN β’ Mar 2, 2007
SILVER MINT & SILVER MINE
Closed β’ AUSTIN β’ Oct 28, 2010
RACETRAC SERVICE STATION
Approved and Released β’ AUSTIN β’ Mar 2, 2007
DAVID WEEKLEY HOMES - NEW HOME CENTER
Approved and Released β’ AUSTIN β’ Mar 2, 2007
WASTEWATER SERVICE EXTENSION NO. 1601
Approved and Released β’ AUSTIN β’ Mar 2, 2007
KOCH MATERIALS WW SERVICE EXTENSION NO. 1601
Approved and Released β’ AUSTIN β’ Mar 2, 2007
Zoning & Land Use
Proposed Use
999, 999
Case Manager
π€
Charles Kanetzky
City of Austin Development Services
Explore Area
π Case Details
Case Number156223
Case TypeSite Plan
Sub Typeβ
Permit NumberSP-99-0230CX
Jurisdictionβ
Property RSN905