Home/Site Plans/WEST BOULDIN CREEK PHASE A2 WASTEWATER SYSTEM IMPROVEMENTS PROJECT
βœ… Approved and Released

WEST BOULDIN CREEK PHASE A2 WASTEWATER SYSTEM IMPROVEMENTS PROJECT

Site plan fully approved and released. All conditions cleared. Ready for construction permitting.

πŸ“ W MARY ST, AUSTIN, TXπŸ“„ Site Plan
Entitled100%
Timeline
Applied: Apr 30, 2003
Updated: Mar 2, 2007
βœ…

Approved and Released

Step 5 of 5: Released βœ“

Site plan fully approved and released. All conditions cleared. Ready for construction permitting.

Next:Pull building permits to begin construction.

πŸ“…Entitlement Timeline

Application Filed
+30d
April 30, 2003
In Review
+1372d
May 30, 2003
Approved
March 2, 2007
Active
July 10, 2003

πŸ“Location & Views

Open in MapsGet Directions|30.24826, -97.76193

🀝 Project Team

🏠 Owner Contact
S
Susan Janek
Coa Department Of Public Works
πŸ“ Applicant Contact
A
Augusto & Karla Villalon

Case Manager

πŸ‘€
Kathy Haught
City of Austin Development Services

πŸ“Œ Case Details

Case Number225544
Case TypeSite Plan
Sub TypeSite Plan Administrative
Permit NumberSP-03-0175D
Jurisdictionβ€”
Property RSN4904