✅ Approved and Released#261107
SHUMAKER DONNELY SITE DEVELOPMENT IMPROVEMENTS
Site plan approved and released. Ready for permit issuance.
📍 11900 TESLA RD, AUSTIN, TX, 78725📄 Site Plan🏛️ AUSTIN 2 MILE ETJ
Entitled100%
Units
—
Density: —
Building
—
FAR: —
Site area
—
City: AUSTIN
Dates
Applied: Oct 27, 2005
Updated: Mar 2, 2007
📊Site Plan Metrics
#261107—
Proposed Units
—
Building Size
—
Site Area
—
Density
FAR:—
Applied:Oct 27, 2005
✅
Approved and Released
Site plan approved and released. Ready for permit issuance.
📅Entitlement Timeline
Application Filed
October 27, 2005
🤝 Project Team
Property Owner
Applicant / Developer
🏗️
Murfee Engineering Co. Inc.
View portfolio of site plans
👤 James Scaief📞 5123279204
📐 Nearby Site Plans
SAND HILL ENERGY CENTER COLORADO RIVER DISCHARGE ACCESS ROAD AND STRUCTURE (RESU
Approved and Released • AUSTIN • Feb 15, 2011
SAND HILL ENERGY CENTER COLORADO RIVER DISCHARGE ACCESS ROAD AND STRUCTURE
Withdrawn • AUSTIN • Mar 2, 2007
SAND HILL ENERGY CENTER
Approved and Released • AUSTIN • Mar 2, 2007
SAND HILL ENERGY CENTER COLORADO RIVER DISCHARGE ACCESS ROAD AND STRUCTURE (RESU
Approved and Released • AUSTIN • Mar 2, 2007
SAND HILL ENERGY CENTER
Approved and Released • AUSTIN • Mar 2, 2007
Line P South Phase 2 Replacement Project
Expired • AUSTIN • Aug 15, 2024
HORNSBY GLEN LIFT STATION AND FORCE MAIN
Expired • AUSTIN • Mar 2, 2007
SOUTH AUSTIN REGIONAL WASTEWATER TREATMENT PLANT DECHLORINATION
Approved and Released • AUSTIN • Mar 2, 2007
SARWWTP TRAIN C SOUTH
Approved and Released • AUSTIN • Mar 2, 2007
SARWWTP-TRAIN C NEW ELECTRICAL SUBSTATION
Approved and Released • AUSTIN • Mar 2, 2007
SARWWTP TRAIN C NORTH
Approved and Released • AUSTIN • Mar 2, 2007
SARWWTP-LIFT STATION AND INFLUENT FLOW SPLIT
Approved and Released • AUSTIN • Mar 2, 2007
Zoning & Land Use
Proposed Use
999
Case Manager
👤
Kathy Haught
City of Austin Development Services
📌 Case Details
Case TypeSite Plan
Sub TypeSite Plan Administrative
Permit NumberSP-05-1634D
JurisdictionAUSTIN 2 MILE ETJ
Property RSN3157722