๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

CSJ:0918-45-368 STP 97(433)MM

PETERSON LN TO ALPHA RD, Dallas, TX 75154, Dallas, TX, 75154
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB0000761
$74K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
4y 8mo
Duration
Registered:Feb 1, 2010
Start:May 1, 2010
Target:Dec 16, 2014
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

WIDEN 4-LANE FACILITY TO 5-LANE FACILITYBI/IV PD $775 04122010 RR#02149971

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 1, 2010
Construction Start
May 1, 2010
Expected Completion
December 16, 2014