๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

RENOVATIONS TO FIELD ELEMENTARY SCHOOL

703 EAST 17TH ST., Houston, TX 77008, Houston, TX, 77008
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB0813989
$695K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
7 months
Duration
Registered:Jul 19, 2010
Start:Jan 1, 2011
Target:Aug 1, 2011
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Various site and interior renovationsVAR175

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 19, 2010
Construction Start
January 1, 2011
Expected Completion
August 1, 2011