NORTH AND SOUTH HOLLY WTP CONVERSION
920 FOURNTER ST, Fort Worth, TX 76102, Fort Worth, TX, 76102
Completed100%
๐Project Metrics
TDLR #EABPRJB1810999$2.5M
Project Value
โ
Square Feet
โ
Cost/SqFt
11 months
Duration
Registered:Apr 25, 2011
Start:Aug 1, 2011
Target:Jul 1, 2012
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Replace gaseous chlorine and ammonia tanks and feed equipment with liquid storage tanks and feed equipment.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 25, 2011
Project Closed
July 1, 2012
Construction Start
August 1, 2011
Expected Completion
July 1, 2012
Property Owner
๐ค
City of Fort Worth
Contact: Registered by TDLR
4 projects ยท $11.0M
View company profile
CHRIS HARDER 1511 11TH AVENUE, FORT WORTH, TX 76102
Design Firm
๐๏ธ
Carollo Engineers, Inc.
View company profile
JIM GALLOVICH 100 E. 15TH ST, STE 300, FORT WORTH, TX 76102