๐ŸProject Closed๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

CARROLL HIGH SCHOOL 2011 ADDITIONS & REN

800 N. WHITE CHAPEL, Southlake, TX 76092, Southlake, TX, 76092
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB2804048
$6.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
7 months
Duration
Registered:Nov 23, 2011
Start:Dec 1, 2011
Target:Jul 1, 2012
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Classroom addition, Art wing addition, Fieldhouse

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 23, 2011
Construction Start
December 1, 2011
Expected Completion
July 1, 2012