๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

SIENNA MUD 3 SIDEWALKS

9209 !/2 SPOTTED OWL WAY, Missouri City, TX 77459, Missouri City, TX, 77459
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB3807047
$53K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
3 months
Duration
Registered:Jan 19, 2013
Start:Feb 1, 2013
Target:May 1, 2013
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Concrete sidewalks connecting existing curbs

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 19, 2013
Construction Start
February 1, 2013
Expected Completion
May 1, 2013