NED GRANGER BLDG 5TH FLOOR RENOVATION
๐Project Metrics
TDLR #EABPRJB3809113Project Closed
Project has been completed and closed
๐Scope of Work
Interior remodel of the 5th floor suite 500. Will consist of 21K sf and will house the CA dept, type B occupanc
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
๐Related Projects
๐คSame Owner
$4.5M total๐๏ธSame Design Firm
$1.3M total๐Related City Permits
Building permits found at or near this location
Request to disconnect Upgrade overhead service to 325 Amps.
Install new gas line for generator
Scope of Work: Full gas line replacement. Replace the complete poly gas line in ground with a new 1ยฟ poly gas line. The new gas line will be high pressure with regulators at both the pool heater and the fire pit.
Pre-Plumbed Water Softener Install
Replacing existing Cummins 35kW generator with new Generac 60kW whole home generator (Natural Gas) connected to house subpanels. No disconnect required. (Chris Easley)