Project has been completed and closed
GRIFOLS 2ND FLOOR OFFICES is a Renovation/Alteration project located at 201 CARLSON CIRCLE, San Marcos, TX 78666 in San Marcos, Texas. The project has an estimated value of $209K. GRIFOLS is the property owner and WESLEY A STEELE ARCHITECT is the design firm of record. The project was registered with TDLR on January 8, 2014.
GRIFOLS 2ND FLOOR OFFICES is a renovation/alteration project at 201 CARLSON CIRCLE, San Marcos, TX 78666 in San Marcos, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Add (3) new enclosed offices and (1) open office space space as well as (1) new stair in warehouse area.
Construction on GRIFOLS 2ND FLOOR OFFICES is complete โ TDLR records show the project passed its required accessibility inspection in May 2014. The building is finished and very likely open.
GRIFOLS 2ND FLOOR OFFICES is located at 201 CARLSON CIRCLE, San Marcos, TX 78666, San Marcos, TX, 78666, in Hays County.
GRIFOLS is the property owner/developer of record for GRIFOLS 2ND FLOOR OFFICES, per its TDLR project registration.
WESLEY A STEELE ARCHITECT is the design firm of record for GRIFOLS 2ND FLOOR OFFICES, according to its TDLR filing.
GRIFOLS 2ND FLOOR OFFICES has an estimated construction value of $209K, based on its TDLR filing.
Add (3) new enclosed offices and (1) open office space space as well as (1) new stair in warehouse area.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Filed
Jan 8, 2014
Review Complete
Inspection Complete
Closed
May 1, 2014
Building permits found at or near this location
Partially enclosing the front porch area to add to the living room remodeling throughout of floors bathrooms closets and kitchen reinsulating the exterior walls and siding replacement. No change to impervious cover
Tunnel under the foundation to repair a break in the PVC drain line in the master bathroom and hall bathroom with SCH 40 PVC. There will be two access holds in front of and behind the house.
up to a 50 pipe burst to replace the sewer line in yard as well as tunnel up to 50 under the home to replace the cast iron line.
Replacement of complete existing central heat and air system with or without duct work Install replacement of 2.5 Ton AC System
Remove existing pool and replace with a new pool with the same specifications.