๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

HEMISFAIR INTERNAL STREETS IMPROVEMENTS

WATER STREET AND E. NUEVA, San Antonio, TX 78205, San Antonio, TX, 78205
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB5803545
$835K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1y 4mo
Duration
Registered:Oct 24, 2014
Start:Jan 1, 2015
Target:May 1, 2016
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Construct roadway, sidewalks, drainage, utilities, and signals for Water and E. Nueva.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 24, 2014
Construction Start
January 1, 2015
Expected Completion
May 1, 2016