๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

AVALON AT SIENNA PLANTATION PHASE 1:SITE

4802 AVALON PLANTATION DRIVE, Missouri City, TX 77459, Missouri City, TX, 77459
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB5820672
$75K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
2 months
Duration
Registered:Jul 24, 2015
Start:Aug 1, 2015
Target:Oct 1, 2015
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Installation of sidewalks along neighborhood roadways

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 24, 2015
Construction Start
August 1, 2015
Expected Completion
October 1, 2015