๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

TERM D WHITEBOX MEP PATHWAY DESIGN TEMP.

DFW AIRPORT, Dfw Airport, TX 75261, Dfw Airport, TX, 75261
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6807403
$52K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1 months
Duration
Registered:Dec 31, 2015
Start:Jan 1, 2016
Target:Feb 1, 2016
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Build temporary walls at duty free area of construction.Walls to have FIDC installed by Owner.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 31, 2015
Construction Start
January 1, 2016
Expected Completion
February 1, 2016