๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

FIRE SPRINKLER SYSTEM RENOVATION

110 MOODY, Galveston, TX 77550, Galveston, TX, 77550
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6816822
$395K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
2 months
Duration
Registered:May 18, 2016
Start:May 1, 2016
Target:Jul 1, 2016
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Provide fire sprinkler system & minor renovations.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 18, 2016
Construction Start
May 1, 2016
Expected Completion
July 1, 2016