โœ…Inspection Complete๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

KIRBY MIDDLE SCHOOL RENOVATIONS RFCSP 18

5441 OLD SEGUIN ROAD, San Antonio, TX 78219, San Antonio, TX, 78219
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB8816736
$21.5M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
2 years
Duration
Registered:May 9, 2018
Start:Jul 1, 2018
Target:Jul 1, 2020
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Demolition of 4 existing buildings and addition of a new29,500sf +/- Gymnasium, a 35,500sf +/- classroom and ad

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 9, 2018
Construction Start
July 1, 2018
Expected Completion
July 1, 2020