Salado ISD | New Middle School
1248 Williams Road, Salado, TX 76571, Salado, TX, 76571
Completed100%
๐Project Metrics
TDLR #TABS2019002091$36.4M
Project Value
136,956
Square Feet
$266/sqft
Cost/SqFt
2y 6mo
Duration
Registered:Jan 7, 2019
Start:Mar 4, 2019
Target:Aug 11, 2021
๐
Project Closed
Project has been completed and closed
๐Scope of Work
A new middle school for Salado ISD.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 7, 2019
Project Closed
August 11, 2021
Construction Start
March 4, 2019
Expected Completion
August 11, 2021
๐Related Projects
๐คSame Owner
$39.5M totalProperty Owner
๐ค
Salado ISD
Contact: Crystal Vasquez
2 projects ยท $39.5M
View company profile
PO Box 98, Salado, Texas 76571
Design Firm
๐๏ธ
Huckabee
4 projects ยท $83.5M
View company profile
11501 Alterra Parkway Building 7, Ste. 120, Austin, Texas 78758