๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

City of Pearland Orange Street Service Center Phase 1

3501 E Orange Street, Pearland, TX 77584, Pearland, TX, 77584
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019011085
$3.8M
Project Value
19,000
Square Feet
$197/sqft
Cost/SqFt
1 year
Duration
Registered:May 7, 2019
Start:Jul 31, 2019
Target:Jul 31, 2020
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

New 2 story public works administration buildings and associated parking for employees

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 7, 2019
Construction Start
July 31, 2019
Expected Completion
July 31, 2020