๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Main Street Sidewalk Project

Main Street and Broadway, La Porte, TX 77571, La Porte, TX, 77571
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019015310
$300K
Project Value
21,000
Square Feet
$14/sqft
Cost/SqFt
4 months
Duration
Registered:Jul 2, 2019
Start:Oct 1, 2019
Target:Feb 1, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Construct 5' Sidewalk on Main Street from Broadway to Blackwell Street.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 2, 2019
Construction Start
October 1, 2019
Expected Completion
February 1, 2020