๐ŸProject Closed๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Eagle Pass Independent School District

2020 Second Street, Eagle Pass, TX 78852, Eagle Pass, TX, 78852
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019016784
$2.1M
Project Value
11,000
Square Feet
$191/sqft
Cost/SqFt
2y 2mo
Duration
Registered:Jul 23, 2019
Start:Sep 1, 2019
Target:Nov 1, 2021
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

11000 s.f. band hall addition

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 23, 2019
Construction Start
September 1, 2019
Expected Completion
November 1, 2021