โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Kenedy ISD Admin/HS Renovations

401 FM 719, Kenedy, TX 78119, Kenedy, TX, 78119
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019018059
$6.2M
Project Value
46,439
Square Feet
$134/sqft
Cost/SqFt
1y 7mo
Duration
Registered:Aug 9, 2019
Start:Oct 1, 2019
Target:May 1, 2021
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Removal & replacement of existing VCT carpet acoustic clg tiles ltg HVAC. Incorporate new sprinkler system, paint int walls. New bus canopy.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 9, 2019
Construction Start
October 1, 2019
Expected Completion
May 1, 2021