L-CISD Project B: Ag Facility Expansion

16705 CR 2330, Lubbock, TX 79423, Lubbock, TX, 79423
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020011705
$2.2M
Project Value
27,000
Square Feet
$81/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Feb 17, 2020
Start:Apr 1, 2020
Target:Apr 30, 2021
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

New construction for (3) bldg's. consisting of animal housing for sheep and swine. The third bldg. is a management building consisting of training areas, wash pens, exercise room, toilet room, laundry room and site work associated with all (3) bldgs.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 17, 2020
Construction Start
April 1, 2020
Expected Completion
April 30, 2021