๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
Haverty's Southlake
250 North Kimball Avenue, Southlake, TX 76092, Southlake, TX, 76092
Completed100%
๐Project Metrics
TDLR #TABS2020011794$1.2M
Project Value
33,375
Square Feet
$36/sqft
Cost/SqFt
5 months
Duration
Registered:Feb 18, 2020
Start:Mar 16, 2020
Target:Aug 14, 2020
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Interior upfit and exterior entry modification
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 18, 2020
Project Closed
August 14, 2020
Construction Start
March 16, 2020
Expected Completion
August 14, 2020
Property Owner
๐ค
Jason Garrison/RPAI Southwest Management
Contact: Jeffery Kelley
View company profile
1560 E. Southlake Boulevard Suite 100, Southlake, Texas 76092
Design Firm
๐๏ธ
Mcmillan Pazdan Smith
View company profile
434 Marietta Street NW Suite 105, Atlanta, Georgia 30313
Registered Accessibility Specialist
Tenant
๐ข
Mark Russell