๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Lubbock Independent School District Security Hardening for Lubbock High School

2004-19th Street, Lubbock, TX 79401, Lubbock, TX, 79401
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020017093
$500K
Project Value
4,000
Square Feet
$125/sqft
Cost/SqFt
1 year
Duration
Registered:May 11, 2020
Start:Jul 1, 2020
Target:Jul 1, 2021
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Installation of security doors, security partitions, security alarms and controls.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 11, 2020
Construction Start
July 1, 2020
Expected Completion
July 1, 2021